Dear PS Experts,

We have real estate projects (Customer projects), and one typical structure is we have a housing complex project of 100 villas. (We are in process of implementing PS but all other SAP modules like FI/CO, MM, SD, PM, PP, QM etc are existing.)

Now after construction or during construction phase itself, these villas need to be sold through SD sales where following selling scenarios exists.

1. Each villa separately sold to individual customer. 1 S/O per Villa.

2. One S/O with multiple villas (Each villa is line item in S/O)

Here while I structure the project, I considered, two structures as follows,

1. 100 Villa project with project definition ABC/20014/PJ01. One main WBS with 100 WBS under that. Each of this WBS represent one villa and S/O will be assigned with this WBS.

2. 100 Villa project with project definition ABC/20014/PJ01. One main WBS with 4-5 WBS under that (1. Engineering & design 2. Land preperation 3. Construction etc..) and each villa is represented as a network & S/O will be assigned to main WBS and each S/O item will be assigned to these corresponding network of 100.

 

Since there is a huge implications if I structure it incorrectly. hence I would like to hear from you the best possible solutions.

Please share your ideas.

Regards,

VINOD.V


Viewing all articles
Browse latest Browse all 8851

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>